Foothill Freeway (I-210) Closures for Pavement Rehabilitation

The California Dept. of Transportation (Caltrans) will close portions of the Foothill Freeway (I-210), including some on- and off-ramps and connectors as part of a pavement rehabilitation project. Residents and local businesses located near the freeway may experience noise, vibrations and dust associated with construction activities. Water trucks will be used to minimize dust during working hours, and equipment movement during overnight work will be limited to reduce noise from back-up alarms. Some closures may start and end later (up to 1 p.m. the following day). All closures are weather permitting and subject to change.

Long-Term Closures:
Eastbound I-210 Angeles Crest Highway on-ramps through January
Westbound I-210 connector to California/Del Mar/State Route 110 exit intermittently during the week (11 a.m. to 6 a.m., Monday-Friday) through January

I-210 project closures Monday, Jan. 22 through Saturday, Jan. 27:
Eastbound I-210 (7 p.m. to 6 a.m.)
*Up to four lanes from Lowell Avenue to Mountain Street
*Lowell Avenue, La Crescenta Avenue, Foothill Boulevard and Angeles Crest Highway (long-term closure since Jan. 2) on-ramps
*Gould Avenue, Colorado Boulevard,and Angeles Crest Highway off-ramps
*Pennsylvania Avenue, Berkshire Place, Ocean View Boulevard, Arroyo Boulevard/Windsor Avenue, Lincoln Avenue/Howard Street, and Mountain Street on and off-ramps
*Connectors: southbound State Route 2 (Glendale Freeway), southbound I-710 (Long Beach Freeway),westbound SR-134 (Ventura Freeway)

Westbound I-210 (7 p.m. to 6 a.m.)
*Up to four lanes from Walnut Street to Lowell Ave
*Gould Avenue and Walnut Street on-ramps
*Lowell Avenue (no Friday night closure), La Crescenta Avenue and Foothill Boulevard off-ramps
*Berkshire Place, Angeles Crest Highway, Ocean View Boulevard, and Pennsylvania Avenue on and off-ramps
*Connectors: southbound SR-2, southbound I-710 (no Friday night closure)

Northbound SR-2
8 p.m. to 6 a.m. – Verdugo Boulevard off-ramp (7 p.m. Friday to 7 a.m. Saturday)
8 p.m. to 6 a.m. – Foothill Boulevard off-ramp (7 p.m. Friday to 10 a.m. Saturday)
7 p.m. to 6 a.m. – SR-2 connector to eastbound I-210
10 p.m. to 7 a.m. – SR-2 connector to westbound I-210 (11 p.m. Friday to 11 a.m. Saturday)

Southbound SR-2
8 p.m. to 6 a.m. – Verdugo and Foothill boulevards on-ramps (Foothill on-ramp 7 p.m. Friday to 10 a.m. Saturday)

Eastbound SR-134
7 p.m. to 6 a.m. – SR-134 connector to westbound I-210
7 p.m. to 6 a.m. – SR-134 connector to southbound I-710

Northbound I-710
9 p.m. to 7 a.m. – Del Mar Boulevard on-ramp
11 p.m. to 5 a.m. – California Boulevard on-ramp (no Friday night closure)
7 p.m. to 6 a.m. – I-710 connector to westbound SR-134
7 p.m. to 6 a.m. – I-710 connector to eastbound I-210

Southbound I-710
7 p.m. to 7 a.m. – Del Mar Boulevard off-ramp

***The following on/off-ramps will be closed during daytime hours Monday-Thursday***
9 a.m. to 3 p.m., Eastbound I-210 Ocean View Boulevard on-ramp
9 a.m. to 3 p.m., Westbound I-210 Ocean View Boulevard on and off-ramps
Night time closures are necessary to minimize traffic delays and provide a safe work zone for construction crews and drivers. Drivers should plan ahead and use alternate routes.

The work on I-210 is part of a $148.5 million pavement rehabilitation project for a 9.7 mile section from the La Crescenta-Montrose area of Los Angeles County to Pasadena.

The new surface will provide a smoother drive for motorists and reduce the need for maintenance and further closures.

The project started in Sspring 2015, and is scheduled to be complete in summer 2018.